Chapter 6 RATE ANALYSIS MCQs 15 min Score: 0 Attempted: 0/15 Subscribe 1. . Cost of any item is determined per unit quantity of work, by: (A) Estimate (B) Analysis of rates (C) Quotation (D) TenderShow All Answers 2. . The volume of one bag of cement in M.K.S system is: (A) 0.035 Cum (B) 0.025 Cum (C) 0.35 Cum (D) 0.25 CumShow All Answers 3. . Volume of one bag of cement is: (A) 2.00 Cft (B) 1.50 Cft (C) 1.75 Cft (D) 1.25 CftShow All Answers 4. . Weight of one bag of cement is: (A) 40 Kg (B) 50 Kg (C) 55 Kg (D) 60 KgShow All Answers 5. . Dry volume of concrete is always more than its wet volume, by: (A) 1.45 % (B) 1.50 % (C) 1.64 % (D) 1.54 %Show All Answers 6. . The volume of dry concrete is more than wet, due to: (A) Voids (B) Blucking (C) Shrinkage (D) All of theseShow All Answers 7. . Mostly thickness of cement plastering is kept: (A) Β½ β (12mm) (B) 1β (25mm) (C) 1.5β (38mm) (D) ΒΌ β (6mm)Show All Answers 8. . Volume of cement mortar (dry) is taken for brick masonry: (A) 30 % (B) 25 % (C) 15 % (D) 35 %Show All Answers 9. . Bricks will be required for one Cum masonry: (A) 620 No. (B) 550 No. (C) 600 No. (D) 500 No.Show All Answers 10. . Number of bricks taken in 100 Cft masonry work: (A) 750 (B) 1050 (C) 1350 (D) 1550Show All Answers 11. . A table showing quantity of materials required for a particular work: (A) All of these (B) Estimate (C) Analysis of rates (D) Material statementShow All Answers 12. . Contractor profit is added in detailed estimate: (A) 10 % (B) 8 % (C) 05 % (D) 15 %Show All Answers 13. . Which are the overhead charges in rate analysis? (A) Furniture (B) All of these (C) Office rent (D) SalariesShow All Answers 14. . Number of masons required for 100 Cft brickwork is: (A) 2.5 (B) 1.5 (C) 2 (D) 1Show All Answers 15. . Dry material is taken for 100 Cft concrete works: (A) 135 (B) 145 (C) 154 (D) 164Show All Answers