Q1: Why do we need metrics? (2 marks)
Answer: Metrics give better insight into the state of a process or product. They indicate potential problems but are not the problems themselves. Software engineers collect measures, develop metrics, and derive indicators.

Q2: Degree of Rigor? (2 marks)
Answer: The degree of rigor determines the set of tasks to be performed in a project. It can be categorized as:

Q3: Uses of Control Chart (3 marks)
Answer: Control charts determine whether trends are statistically valid and which changes are meaningful. Types include:

Q4: Effect of bug fixes on software quality (5 marks)
Answer: Defect repair/maintenance supports the release functionality specification and may involve fixing bugs or enhancing performance. Proper defect management improves software quality.

Q5: Effort validation (2 marks)
Answer: Ensure that no more than the allocated number of staff members are scheduled at any time during the project.

Q6: Flexibility vs Maintainability (3 marks)
Answer:

Q7: Effect of decreasing spoilage on maintainability (3 marks)
Answer: Spoilage cost measures the cost to correct defects after release. Decreasing spoilage indicates improved maintainability.

Q8: Define “Baseline Data”
Answer: Baseline data is collected from past projects, cleaned, and stored in a database. It is used for estimation, process improvement, and performance analysis.

Q9: Differentiate between Casual and Structured Rigor (2 marks)
Answer:

Q10: Can we guarantee 100% risk-free software? (5 marks)
Answer: No. Software development always involves risk. Not taking action is also a risk. Risk can be mitigated through careful planning and the ability to undo mistakes.

Q11: ILFs vs EIFs (3 marks)
Answer: Both are user-identifiable groups of data.

Q12: What is Risk Projection?
Answer: Risk projection estimates and rates risks based on likelihood and consequences. Steps include:

Q13: Can a logical file be counted as both ILF and EIF?
Answer: No. A logical file satisfying both rules is counted as an ILF only.

Q14: Role of interdependency and time allocation in project schedule
Answer:

Numerical / Diagram Questions

Q15: Draw a moving range control chart

Given Data: Project: 1 2 3 4 5
Data: 4 3 1 3 5

Answer:

ProjectValueRange (difference from previous)
14
231
312
432
552

Q16: Lack of Ambiguity Calculation

Given: Nf = 25, Nnf = 5, Nui = 10

Formula (typical):

Lack of Ambiguity=NfNf+Nnf+Nui=2525+5+10=2540=0.625\text{Lack of Ambiguity} = \frac{Nf}{Nf + Nnf + Nui} = \frac{25}{25 + 5 + 10} = \frac{25}{40} = 0.625Lack of Ambiguity=Nf+Nnf+NuiNf​=25+5+1025​=4025​=0.625

Q17: Factors in deciding to develop from scratch or use 3rd party software
Answer: Consider:

Q18: Product stability based on defect/fix graph
Answer: If the gap between defects reported and defects fixed is increasing → Product is unstable.