1. .1: An association controlling accidents in any project.
(A) Safety Committee
(B) Management
(C) Workers Union
(D) Rescue 1122
2. .2: Safety Measure against accidents.
(A) Safety Committee
(B) Safety Habits
(C) Safety Campaign
(D) All of these
3. .3: Arrangement of suitable Light at site.
(A) Ventilation
(B) Illumination
(C) Flux
(D) Natural Light
4. .4: Arrangement of fresh Air at site.
(A) Blower
(B) Illumination
(C) Flux
(D) Ventilation
5. .5: Main sources of noise.
(A) Industries
(B) Transport
(C) House hold
(D) All of these
6. .6: Physical bad effect of noise.
(A) All of these
(B) Deaf
(C) Shrinkage of arteries
(D) Headache
7. .7: Psychological bad effect of noise.
(A) Deaf
(B) Depression
(C) Headache
(D) All of these
8. .8: Method of Noise Control.
(A) All of these
(B) Use of new machinery
(C) Use of earmuff
(D) Insulation
9. .9: Alarm system is used for in buildings.
(A) Water Flow
(B) Ventilation
(C) Fire
(D) All of these
10. .10: Fire extinguishing arrangement.
(A) Fire Control Devices
(B) Fire hydrant
(C) Emergency Alarming system
(D) All of these
11. .11: Basic Components of Scaffolding is.
(A) Ledgers
(B) Sole plates
(C) Clamps
(D) Battens
12. .12: Surface used to shape the wet concrete is called.
(A) Die
(B) Form work
(C) Mould
(D) Panel
13. .13: Structure consisting of two side bars between a series of bar/ring set at suitable distance is called.
(A) Ladder
(B) Crowbar
(C) Runner
(D) Stair
14. .14: Temporary platform used to hold the wet concrete is called.
(A) Formwork
(B) Shuttering
(C) Pilling
(D) Drilling
15. .15: Method of timbering is.
(A) Bracing
(B) Sheeting
(C) Piling
(D) All of these
16. .16: Mostly used form work in ordinary concrete work.
(A) Aluminum
(B) Steel
(C) Wooden
(D) Fabric
17. .17: Continued type of formwork is called.
(A) Sheet formwork
(B) Jump formwork
(C) Panel formwork
(D) Slip formwork
18. .18: Steel ladder did not used for.
(A) Plumbing work
(B) Electric work
(C) Sheeting work
(D) Form work
19. .19: Component of timbering is.
(A) Strut
(B) All of these
(C) Wedges
(D) Polling
20. .20: Method for operation of blasting is.
(A) All of these
(B) Drilling
(C) Detonating the charge
(D) Clearing way
21. .21: Removal of ground water from construction site is called.
(A) Pumping
(B) Dewatering
(C) Removing
(D) All of these