T4Tutorials .PK

Installation Planning & Estimating MCQs – DAE Electrical Engineering

1. The first step in electrical installation work is:

(A) Load estimation


(B) Wiring layout design


(C) Site inspection


(D) Material purchasing



2. The main objective of electrical installation planning is to:

(A) Reduce cost and ensure safety


(B) Increase consumption


(C) Avoid drawings


(D) Minimize load



3. The term “IE Rules” stands for:

(A) Indian Electricity Rules


(B) Internal Electrical Rules


(C) Industrial Engineering Rules


(D) Installation Estimation Rules



4. The load of an electrical installation is expressed in:

(A) Amperes


(B) Watts or kilowatts


(C) Volts


(D) Ohms



5. The electrical plan of a building shows:

(A) Ceiling design


(B) Foundation plan


(C) Furniture layout


(D) Wiring layout and switchboard position



6. The diversity factor is always:

(A) Equal to 1


(B) Greater than 1


(C) Less than 1


(D) Zero



7. The demand factor is defined as:

(A) Maximum demand / Connected load


(B) Connected load / Maximum demand


(C) Total load / Connected load


(D) Load factor / Demand factor



8. The permissible voltage drop in lighting circuits should not exceed:

(A) 3%


(B) 5%


(C) 2%


(D) 10%



9. The type of wiring most suitable for temporary installations is:

(A) Conduit wiring


(B) Casing capping


(C) Cleat wiring


(D) Batten wiring



10. In domestic wiring, the most commonly used system is:

(A) Single-phase AC system


(B) Three-phase AC system


(C) DC system


(D) Two-phase system



11. The quantity of materials for estimation is calculated from:

(A) Load chart only


(B) Floor plan only


(C) Ceiling plan


(D) Electrical drawings



12. The point wiring estimate is based on:

(A) Number of points


(B) Load of each circuit


(C) Total wiring length


(D) Type of switches



13. Earthing is provided to:

(A) Improve efficiency


(B) Increase voltage


(C) Protect human life and equipment


(D) Increase resistance



14. The standard voltage for domestic supply in Pakistan is:

(A) 400 V


(B) 110 V


(C) 230 V


(D) 500 V



15. The standard frequency of AC supply in Pakistan is:

(A) 50 Hz


(B) 60 Hz


(C) 45 Hz


(D) 25 Hz



16. The term “schedule of material” means:

(A) List of all required materials with quantity


(B) Labour schedule


(C) Time schedule


(D) Installation order



17. The connected load is the:

(A) Load consumed at one time


(B) Average load used


(C) Total load of all equipment connected


(D) Load factor



18. A sub-circuit should not exceed a load of:

(A) 800 watts


(B) 1000 watts


(C) 1500 watts


(D) 3000 watts



19. For lighting, the maximum number of points in a circuit is:

(A) 10


(B) 5


(C) 8


(D) 12



20. The maximum load of a power circuit is:

(A) 1500 W


(B) 1000 W


(C) 500 W


(D) 3000 W



21. The unit of energy consumed in billing is:

(A) Kilowatt-hour (kWh)


(B) Joule


(C) Watt-second


(D) Megajoule



22. The neutral wire is always:

(A) Used for earthing


(B) At high potential


(C) At or near earth potential


(D) Current-free



23. The most accurate method of electrical estimation is:

(A) Quick estimate


(B) Rough estimate


(C) Approximate estimate


(D) Detailed estimate



24. A typical domestic wiring system includes:

(A) Only power circuits


(B) Only lighting circuits


(C) Lighting and power circuits


(D) Control circuits only



25. The total cost of installation includes:

(A) Material + Labour + Overhead charges


(B) Only material cost


(C) Labour cost only


(D) Miscellaneous charges only



26. Labour cost is generally taken as:

(A) 5% of material cost


(B) 50% of material cost


(C) 10–20% of material cost


(D) 100% of material cost



27. The over-head charges are taken as:

(A) 10% of total cost


(B) 25% of total cost


(C) 5% of total cost


(D) 50% of total cost



28. The rate per point method is used in:

(A) Substation estimation


(B) Transmission line work


(C) Small wiring installations


(D) Industrial plants



29. The wiring diagram shows:

(A) Physical location of electrical components


(B) Only ratings of components


(C) Load current


(D) Cable size



30. A load factor of 0.8 means:

(A) Voltage is reduced by 20%


(B) Efficiency is 80%


(C) Demand is 80% of load


(D) Load used is 80% of maximum demand



31. The type of wiring used in industries is usually:

(A) Conduit wiring


(B) Cleat wiring


(C) Casing-capping wiring


(D) Batten wiring



32. For three-phase supply, the number of conductors required are:

(A) 4


(B) 3


(C) 2


(D) 5



33. The current-carrying capacity of a wire depends on:

(A) Length of wire


(B) Cross-sectional area


(C) Color of insulation


(D) Type of switch used



34. In estimating work, wastage of material is generally taken as:

(A) 5%


(B) 10%


(C) 15%


(D) 2%



35. The main function of a distribution board is to:

(A) Distribute electrical energy to sub-circuits


(B) Store electricity


(C) Step down voltage


(D) Protect cables only



36. The ISI symbol on electrical materials means:

(A) Imported product


(B) Product made in India


(C) Product meets safety standards


(D) Low-cost item



37. The supply to a building is given through:

(A) Service main


(B) Substation


(C) Transmission line


(D) Switchboard



38. The size of the main switch depends upon:

(A) Total load of installation


(B) Number of lights


(C) Size of fuses


(D) Building height



39. The cost of electrical installation for residential buildings is generally:

(A) 25%


(B) 1–3%


(C) 15–20%


(D) 8–12% of total building cost



40. In industrial wiring, the most important factor is:

(A) Safety and durability


(B) Color of wire


(C) Interior design


(D) Aesthetic look



41. The standard size of conduit used in domestic wiring is:

(A) 40 mm


(B) 10 mm


(C) 19 mm


(D) 60 mm



42. For estimation, the area of a building is calculated in:

(A) Cubic meters


(B) Square meters


(C) Linear meters


(D) Kilometers



43. The cost of earthing set is generally included under:

(A) Material charges


(B) Labour charges


(C) Overhead charges


(D) Miscellaneous charges



44. The main switch is always installed:

(A) Near the main entrance


(B) Inside the bedroom


(C) Near the ceiling


(D) In the kitchen



45. The length of wire for estimation is increased by:

(A) 5%


(B) 50%


(C) 25%


(D) 10% for wastage and connections



46. The lighting load per square meter in a residential building is about:

(A) 20 W/m²


(B) 100 W/m²


(C) 2 W/m²


(D) 10 W/m²



47. The cable size depends on:

(A) Current carrying capacity


(B) Voltage rating


(C) Length of run


(D) All of these



48. The total connected load is used to determine:

(A) Rating of main switch and wires


(B) Color of insulation


(C) Circuit layout only


(D) Building cost



49. The supply from distribution board to sub-circuit is given through:

(A) Isolator


(B) Fuse or MCB


(C) Transformer


(D) Neutral link



50. The final step in electrical installation planning is:

(A) Testing and commissioning


(B) Estimation


(C) Material ordering


(D) Drawing preparation



Exit mobile version